schedule

Virginia Street Project

Two-way Traffic on Virginia Street

We’re more than 95% done with the first phase of the Virginia Street Project and have reopened the entire corridor to two-way traffic. Drivers can still expect to see possible lane closures and traffic shifts as utility companies connect utilities throughout the corridor through the month of April.

Storm Drain Work Planned for April

In early April, the section of Virginia Street from Center Street/Mary Street to Vassar Street will close to one-way traffic to finish a storm drain system that could not be completed until utility companies are finished with their installations. Southbound traffic only is anticipated for about two weeks in early April. Northbound traffic will be detoured. Sierra Nevada Construction will allocate multiple crews to expedite this work.